Roy Hill Project Australia

Mining Industry


Cargo 403.000 cbm / 222.000 Tonnes of project cargo
From Various ports
To Roy Hill project site, Australia
Details SCT initially appointed NMT Global Project Logistics under an Early Contractor Involvement [ECI] arrangement to undertake a full logistics study for the project. This ECI phase included route studies and interfacing with major stakeholders, sub-contractors and government bodies. This involvement led to NMT securing a major contract with SCT for offshore services, the chartering of over 20 vessels, laydown management within NMT’s Port Hedland staging area and onshore delivery of about 403,000 m3 / 222,000 tonnes of cargo. The items we shipped included (but were not limited to) the following:

• Bridge Girders, (Various)
• Concrete Sleepers (Various)
• Processing Plant Modules & Conveyors
• Train Load out Circuit (Mine site)
• Trippers (Port Stockyard)