Project details

SANDVIK - 2 X Coal Stackers for PWCS over 2 x Shipments, 25,760 rt

Cargo collection point

Masan, Korea
Cargo delivery point

Newcastle, Australia
Category

Mining
DESCRIPTION

NMT were contracted by Sandvik Mining and Construction to organise the Movement of 2 x Coal Stackers for the PWCS expansion project. The cargo was pre-inspected for AQIS, and prepared for shipment under supervision from NMT. Once the cargo was uplifted by heavylift Vessels and arrived in newcastle, the heavylift and oversize units that could not be taken by road from the port, were loaded onto a barge and unloaded in close proximity to the PWCS site. Some of the items moved ranged up to 6.5 meters, over 50 meters in length and up to 80 metric tons.